CIVITRACK

Sample dossier pack access

Use the report-pack access code. These are review samples, not certifications, ratings, legal opinions, valuations, or site inspections.

CIVITRACK

10 source-linked sample reports.

Eight road dossiers selected only after external reconciliation found them source-consistent, plus two non-road source-context samples. Every report shows confirmations, gaps, abstains, source routes, contractor/entity context, satellite boundaries, and reviewer questions.

10sample dossiers
8/8road samples source-consistent in Layer B dry run
5road samples with independent Set-A corroboration
0No satellite-derived public progress score
Rs 49,00010-project paid pilot offer
Cross-check process in place. Current road validation set: 120 source-consistent, 91 hold, 61 insufficient external. Hold rows are excluded from this customer sample pack.
ROAD-01 | Roads & Highways | 618864

4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IB

PCC Issued, CC Pending; 100. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618864
Promoted UPCsN/08026/02002/UP
NH / corridorNH-44
Official stage fieldPCC Issued, CC Pending
Official physical field100
Public cost contextRs 1722 Cr
Public revised costRs 1820.77 Cr
Public scheduled completion19/03/2025
Public revised completion01/07/2026
RBI source-backed fields12
Open evidence gaps6

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:6

Independent Set-A: No independent Set-A source confirmed in this dry run; NHAI/PAIMANA source consistency still passed.

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project name4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IBSOURCE_BACKEDSource
Project code618864SOURCE_BACKEDSource
UPCsN/08026/02002/UPSOURCE_BACKEDSource
StagePCC Issued, CC PendingSOURCE_BACKEDSource
Physical progress100SOURCE_BACKEDSource
Sanctioned cost1722SOURCE_BACKEDSource
Revised cost1820.77SOURCE_BACKEDSource
Public schedule19/03/2025SOURCE_BACKEDSource
Public revised schedule01/07/2026SOURCE_BACKEDSource
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route

Confirmed Checks

Stage Of CompletionPCC Issued, CC PendingStage maps to same normalized Data Lake vocabulary family: pcc_issued_cc_pending.NHAI Data Lake
Physical Progress100Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextPNC Infratech Pvt. Ltd.UPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH44; NH530BAt least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 1722.11 Cr; awarded/civil cost Rs 885 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

SPV_SPONSOR_SEPARATED
NHAI Data Lake contractor textPNC Infratech Pvt. Ltd.
Concessionaire SPVYamuna Highways Pvt Ltd (HAM)
Listed sponsorPNC Infratech Limited (L45201DL1999PLC195937)
MCA statusActive; ROC ROC Delhi I; incorporated 09/08/1999
Directors / signatories11 public MCA director/signatory row(s) parsed
Open charges context36 open charge(s); Rs 6308.6407 Cr aggregate shown as lien context only
EWS context bandAMBER - RBI EWS framing only, not a CiviTrack rating
Listed financialsRevenue Rs 5368 Cr; PAT Rs 832 Cr; net worth Rs 6813 Cr; debt Rs 5170 Cr; order book Rs 19261 Cr
Cost basis noteRs 1,722.11 Cr NHAI Data Lake / PAIMANA project basis; Rs 885 Cr PNC exchange disclosure. Different official bases, not a contradiction.

Open Gaps And Abstains

  • project_identity.chainage
  • contractor_cin
  • borrower_concessionaire_spv_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
Mixed PackageN/08026/02002/UP: PCC Issued, CC Pending; 100%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Iig Nip Identityproject code=618864; project name=4L from Mathura Bypass Start at Existing Km. 154.20 of NH-44 to Gaju Village at Km 32.982 of NH-530B Pkg-IB; nh tokens=NH44, NH530BNo exact IIG/NIP project-id match in local public crawl.IIG / NIP
Eprocure Aoc Awardpromoted upcs=N/08026/02002/UP; nhai award evidence=upc=N/08026/02002/UP; contractor name=PNC Infratech Pvt. Ltd.; awarded cost cr=885; date values=loa date=29-03-2022; agreement date=20-07-2022No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-02 | Roads & Highways | 617982

Widening and strengthening of existing 2-lane to 2- lane with paved shoulders from km 159/0 to 165/4 and 186/0 to 215/0 of NH-163 on EPC mode int the state of Telangana

Under Construction (AD issued); Under Construction (AD issued). Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code617982
Promoted UPCsN/06003/01003/TS
NH / corridorNH-163
Official stage fieldUnder Construction (AD issued)
Official physical fieldUnder Construction (AD issued)
Public cost contextRs 230 Cr
Public revised costRs EVIDENCE_PENDING Cr
Public scheduled completion30/11/2019
Public revised completion03/12/2020
RBI source-backed fields11
Open evidence gaps6

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:5

Independent Set-A: iig_nip

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project nameWidening and strengthening of existing 2-lane to 2- lane with paved shoulders from km 159/0 to 165/4 and 186/0 to 215/0 of NH-163 on EPC mode int the state of TelanganaSOURCE_BACKEDSource
Project code617982SOURCE_BACKEDSource
UPCsN/06003/01003/TSSOURCE_BACKEDSource
StageUnder Construction (AD issued)SOURCE_BACKEDSource
Physical progressUnder Construction (AD issued)SOURCE_BACKEDSource
Sanctioned cost230SOURCE_BACKEDSource
Revised costEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Public schedule30/11/2019SOURCE_BACKEDSource
Public revised schedule03/12/2020SOURCE_BACKEDSource
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGNOT_APPLICABLESource
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route
  • IIG / NIPIndependent Set-A corroboration. Unreachable or absent sources are never counted as a pass.Open source route

Confirmed Checks

Stage Of CompletionUnder Construction (AD issued)Stage maps to same normalized Data Lake vocabulary family: under_construction.NHAI Data Lake
Contractor TextSarath Chandra ConstructionsUPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH163At least one NH token overlaps after title-token normalization.NHAI Data Lake
Iig Nip Identityiig project id=617982; project name=Widening and strengthening of existing 2-lane to 2- lane with paved shoulders from km 159/0 to 165/4 and 186/0 to 215/0 of NH-163 on EPC mode int the state of Telangana; state=Telangana; cost display=USD 28.92 mnIndependent IIG/NIP exact project-id match corroborates project identity; not used as progress truth.IIG / NIP

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textSarath Chandra Constructions
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • project_identity.chainage
  • contractor_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
  • revised_cost
Mixed PackageN/06003/01003/TS: Under Construction (AD issued)Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Physical ProgressCheckedPhysical progress missing on one side.NHAI Data Lake
Cost Basisawarded/civil cost Rs 35 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.LABELLED_BASIS_DIFFERENCE: public cost and NHAI package/capital/award cost use different official bases; not a contradiction without independent basis evidence.NHAI Data Lake
Eprocure Aoc Awardpromoted upcs=N/06003/01003/TS; nhai award evidence=upc=N/06003/01003/TS; contractor name=Sarath Chandra Constructions; awarded cost cr=35; date values=loa date=27-03-2025; agreement date=21-05-2025No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-03 | Roads & Highways | 618397

Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis

Under Construction (AD issued); 62.81. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618397
Promoted UPCsN/09106/01001/JK
NH / corridorNH-244
Official stage fieldUnder Construction (AD issued)
Official physical field62.81
Public cost contextRs 256 Cr
Public revised costRs EVIDENCE_PENDING Cr
Public scheduled completion21/11/2020
Public revised completion04/02/2022
RBI source-backed fields12
Open evidence gaps5

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:6

Independent Set-A: iig_nip

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project nameWidening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basisSOURCE_BACKEDSource
Project code618397SOURCE_BACKEDSource
UPCsN/09106/01001/JKSOURCE_BACKEDSource
StageUnder Construction (AD issued)SOURCE_BACKEDSource
Physical progress62.81SOURCE_BACKEDSource
Sanctioned cost256SOURCE_BACKEDSource
Revised costEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Public schedule21/11/2020SOURCE_BACKEDSource
Public revised schedule04/02/2022SOURCE_BACKEDSource
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGNOT_APPLICABLESource
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route
  • IIG / NIPIndependent Set-A corroboration. Unreachable or absent sources are never counted as a pass.Open source route

Confirmed Checks

Stage Of CompletionUnder Construction (AD issued)Stage maps to same normalized Data Lake vocabulary family: under_construction.NHAI Data Lake
Physical Progress62.81Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextSRM Contractors Limited - DMR Builders Private Limited (JV)UPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH244At least one NH token overlaps after title-token normalization.NHAI Data Lake
Iig Nip Identityiig project id=618397; project name=Widening and Up-gradation to 2-Lane with Paved Shoulder of configuration and geometric improvement from Km 0.000 to Km 16.990 on Chenani Sudhmahadev section of NH-244 in UT of Jammu and Kashmir to be executed on EPC basis; state=Jammu and Kashmir; cost display=USD 32.18 mnIndependent IIG/NIP exact project-id match corroborates project identity; not used as progress truth.IIG / NIP

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textSRM Contractors Limited - DMR Builders Private Limited (JV)
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • contractor_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
  • revised_cost
Mixed PackageN/09106/01001/JK: Under Construction (AD issued); 62.81%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Cost Basistotal capital cost Rs 295.06 Cr; awarded/civil cost Rs 236 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.LABELLED_BASIS_DIFFERENCE: public cost and NHAI package/capital/award cost use different official bases; not a contradiction without independent basis evidence.NHAI Data Lake
Eprocure Aoc Awardpromoted upcs=N/09106/01001/JK; nhai award evidence=upc=N/09106/01001/JK; contractor name=SRM Contractors Limited - DMR Builders Private Limited (JV); awarded cost cr=236; date values=loa date=11-03-2024; agreement date=03-07-2024No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-04 | Roads & Highways | 618582

4L of Galgalia - Bahadurganj section from Km 0.000 to Km 49.000 Package-I of NH327E

CC Issued; 100. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618582
Promoted UPCsN/03012/02001/BR
NH / corridorNH-327E
Official stage fieldCC Issued
Official physical field100
Public cost contextRs 1283 Cr
Public revised costRs 1282.97 Cr
Public scheduled completion09/01/2024
Public revised completionEVIDENCE_PENDING
RBI source-backed fields12
Open evidence gaps6

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:7

Independent Set-A: iig_nip

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project name4L of Galgalia - Bahadurganj section from Km 0.000 to Km 49.000 Package-I of NH327ESOURCE_BACKEDSource
Project code618582SOURCE_BACKEDSource
UPCsN/03012/02001/BRSOURCE_BACKEDSource
StageCC IssuedSOURCE_BACKEDSource
Physical progress100SOURCE_BACKEDSource
Sanctioned cost1283SOURCE_BACKEDSource
Revised cost1282.97SOURCE_BACKEDSource
Public schedule09/01/2024SOURCE_BACKEDSource
Public revised scheduleEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route
  • IIG / NIPIndependent Set-A corroboration. Unreachable or absent sources are never counted as a pass.Open source route

Confirmed Checks

Stage Of CompletionCC IssuedStage maps to same normalized Data Lake vocabulary family: completed.NHAI Data Lake
Physical Progress100Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextGR Infra Projects LtdUPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH327EAt least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 1282.97 Cr; awarded/civil cost Rs 1051 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake
Iig Nip Identityiig project id=618582; project name=4L of Galgalia - Bahadurganj section from Km 0.000 to Km 49.000 Package-I of NH327E; state=Bihar; cost display=USD 161.32 mnIndependent IIG/NIP exact project-id match corroborates project identity; not used as progress truth.IIG / NIP

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textGR Infra Projects Ltd
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • contractor_cin
  • borrower_concessionaire_spv_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
  • public_revised_scheduled_completion_date
Mixed PackageN/03012/02001/BR: CC Issued; 100%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Eprocure Aoc Awardpromoted upcs=N/03012/02001/BR; nhai award evidence=upc=N/03012/02001/BR; contractor name=GR Infra Projects Ltd; awarded cost cr=1051; date values=loa date=03-03-2021; agreement date=17-04-2021No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-05 | Roads & Highways | 618583

4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 Package-II of NH-327E

CC Issued; 100. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618583
Promoted UPCsN/03012/03001/BR
NH / corridorNH-327E
Official stage fieldCC Issued
Official physical field100
Public cost contextRs 1359 Cr
Public revised costRs 1358.77 Cr
Public scheduled completion09/01/2024
Public revised completion12/05/2024
RBI source-backed fields14
Open evidence gaps4

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:7

Independent Set-A: iig_nip

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project name4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 Package-II of NH-327ESOURCE_BACKEDSource
Project code618583SOURCE_BACKEDSource
UPCsN/03012/03001/BRSOURCE_BACKEDSource
StageCC IssuedSOURCE_BACKEDSource
Physical progress100SOURCE_BACKEDSource
Sanctioned cost1359SOURCE_BACKEDSource
Revised cost1358.77SOURCE_BACKEDSource
Public schedule09/01/2024SOURCE_BACKEDSource
Public revised schedule12/05/2024SOURCE_BACKEDSource
Contractor CINcin=U45201GJ1995PLC098652; canonical name=G R Infraprojects Limited; company status=Active; upc=N/03012/03001/BRSOURCE_BACKEDSource
Concessionaire SPV CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route
  • IIG / NIPIndependent Set-A corroboration. Unreachable or absent sources are never counted as a pass.Open source route

Confirmed Checks

Stage Of CompletionCC IssuedStage maps to same normalized Data Lake vocabulary family: completed.NHAI Data Lake
Physical Progress100Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextG R Infraprojects LimitedUPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH327EAt least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 1358.77 Cr; awarded/civil cost Rs 1081.7 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake
Iig Nip Identityiig project id=618583; project name=4L of Bahadurganj Araria section from Km 49.000 to Km 94.000 Package-II of NH-327E; state=Bihar; cost display=USD 170.85 mnIndependent IIG/NIP exact project-id match corroborates project identity; not used as progress truth.IIG / NIP

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textG R Infraprojects Limited
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • borrower_concessionaire_spv_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
Mixed PackageN/03012/03001/BR: CC Issued; 100%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Eprocure Aoc Awardpromoted upcs=N/03012/03001/BR; nhai award evidence=upc=N/03012/03001/BR; contractor name=G R Infraprojects Limited; awarded cost cr=1081.7; date values=loa date=03-03-2021; agreement date=17-04-2021No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adversechecked no adverse=cin=U45201GJ1995PLC098652; contractor=cin=U45201GJ1995PLC098652; canonical name=G R Infraprojects Limited; company status=Active; upc=N/03012/03001/BR; ibbi checked=true; ibbi adverse=falseIBBI exact-CIN page checked with no adverse public announcement; absence is not treated as confirmation.IBBI
Contractor CINcin=U45201GJ1995PLC098652; canonical name=G R Infraprojects Limited; company status=Active; upc=N/03012/03001/BRNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-06 | Roads & Highways | 618631

6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 162.5 to Km. 203.100 in Raichur of NH-150C Pkg-IV

PCC Issued, CC Pending; 99.51. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618631
Promoted UPCsN/04008/03004/KA
NH / corridorNH-150C
Official stage fieldPCC Issued, CC Pending
Official physical field99.51
Public cost contextRs 1500 Cr
Public revised costRs 1457.48 Cr
Public scheduled completion13/05/2025
Public revised completion30/06/2026
RBI source-backed fields14
Open evidence gaps4

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:7

Independent Set-A: iig_nip

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project name6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 162.5 to Km. 203.100 in Raichur of NH-150C Pkg-IVSOURCE_BACKEDSource
Project code618631SOURCE_BACKEDSource
UPCsN/04008/03004/KASOURCE_BACKEDSource
StagePCC Issued, CC PendingSOURCE_BACKEDSource
Physical progress99.51SOURCE_BACKEDSource
Sanctioned cost1500SOURCE_BACKEDSource
Revised cost1457.48SOURCE_BACKEDSource
Public schedule13/05/2025SOURCE_BACKEDSource
Public revised schedule30/06/2026SOURCE_BACKEDSource
Contractor CINcin=L45200MH1993PLC071970; canonical name=Ashoka Buildcon Limited; company status=ACTV; upc=N/04008/03004/KASOURCE_BACKEDSource
Concessionaire SPV CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route
  • IIG / NIPIndependent Set-A corroboration. Unreachable or absent sources are never counted as a pass.Open source route

Confirmed Checks

Stage Of CompletionPCC Issued, CC PendingStage maps to same normalized Data Lake vocabulary family: pcc_issued_cc_pending.NHAI Data Lake
Physical Progress99.51Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextAshoka Buildcon LimitedUPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH150CAt least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 1499.73 Cr; awarded/civil cost Rs 987.68 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake
Iig Nip Identityiig project id=618631; project name=6L of MH/KN Border Nimbal Village to KN/TS Border Singnodi Village from Km. 162.5 to Km. 203.100 in Raichur of NH-150C Pkg-IV; state=Karnataka,Telangana; cost display=USD 183.26 mnIndependent IIG/NIP exact project-id match corroborates project identity; not used as progress truth.IIG / NIP

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textAshoka Buildcon Limited
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • borrower_concessionaire_spv_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
Mixed PackageN/04008/03004/KA: PCC Issued, CC Pending; 99.51%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Eprocure Aoc Awardpromoted upcs=N/04008/03004/KA; nhai award evidence=upc=N/04008/03004/KA; contractor name=Ashoka Buildcon Limited; awarded cost cr=987.68; date values=loa date=30-03-2022; agreement date=17-05-2022No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adversechecked no adverse=cin=L45200MH1993PLC071970; contractor=cin=L45200MH1993PLC071970; canonical name=Ashoka Buildcon Limited; company status=ACTV; upc=N/04008/03004/KA; ibbi checked=true; ibbi adverse=falseIBBI exact-CIN page checked with no adverse public announcement; absence is not treated as confirmation.IBBI
Contractor CINcin=L45200MH1993PLC071970; canonical name=Ashoka Buildcon Limited; company status=ACTV; upc=N/04008/03004/KANo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-07 | Roads & Highways | 618529

Varanasi Ring Road Pkg-II connecting Sandaha Village km 11.70 / NH-29 with Revasa Village km 818.80 / NH-2

Under Construction (AD issued); 94.8. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618529
Promoted UPCsN/02005/11001/UP
NH / corridorNH-29
Official stage fieldUnder Construction (AD issued)
Official physical field94.8
Public cost contextRs 1992 Cr
Public revised costRs 1832.66 Cr
Public scheduled completion13/02/2022
Public revised completion31/10/2026
RBI source-backed fields12
Open evidence gaps5

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:6

Independent Set-A: No independent Set-A source confirmed in this dry run; NHAI/PAIMANA source consistency still passed.

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project nameVaranasi Ring Road Pkg-II connecting Sandaha Village km 11.70 / NH-29 with Revasa Village km 818.80 / NH-2SOURCE_BACKEDSource
Project code618529SOURCE_BACKEDSource
UPCsN/02005/11001/UPSOURCE_BACKEDSource
StageUnder Construction (AD issued)SOURCE_BACKEDSource
Physical progress94.8SOURCE_BACKEDSource
Sanctioned cost1992SOURCE_BACKEDSource
Revised cost1832.66SOURCE_BACKEDSource
Public schedule13/02/2022SOURCE_BACKEDSource
Public revised schedule31/10/2026SOURCE_BACKEDSource
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGNOT_APPLICABLESource
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route

Confirmed Checks

Stage Of CompletionUnder Construction (AD issued)Stage maps to same normalized Data Lake vocabulary family: under_construction.NHAI Data Lake
Physical Progress94.8Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextGammon Engineers & Contractors Pvt. Ltd.UPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH2; NH29; NH31At least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 1991.71 Cr; awarded/civil cost Rs 949 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textGammon Engineers & Contractors Pvt. Ltd.
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • project_identity.chainage
  • contractor_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
Mixed PackageN/02005/11001/UP: Under Construction (AD issued); 94.8%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Iig Nip Identityproject code=618529; project name=Varanasi Ring Road Pkg-II connecting Sandaha Village km 11.70 / NH-29 with Revasa Village km 818.80 / NH-2; nh tokens=NH2, NH29No exact IIG/NIP project-id match in local public crawl.IIG / NIP
Eprocure Aoc Awardpromoted upcs=N/02005/11001/UP; nhai award evidence=upc=N/02005/11001/UP; contractor name=Gammon Engineers & Contractors Pvt. Ltd.; awarded cost cr=949; date values=loa date=13-02-2018; agreement date=24-08-2018No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
ROAD-08 | Roads & Highways | 618560

Improvement of Geometrics of Thondupally to Kothur from Km 22.300 to Km 34.14 of NH-44

Terminated; 17.05. Source-consistent across promoted UPC checks.

SOURCE_CONSISTENT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code618560
Promoted UPCsN/02010/01002/TS
NH / corridorNH-44
Official stage fieldTerminated
Official physical field17.05
Public cost contextRs 542 Cr
Public revised costRs 527.43 Cr
Public scheduled completion16/09/2024
Public revised completionEVIDENCE_PENDING
RBI source-backed fields12
Open evidence gaps5

Cross-Check Verdict

SOURCE_CONSISTENT

set_a_confirmations:6

Independent Set-A: No independent Set-A source confirmed in this dry run; NHAI/PAIMANA source consistency still passed.

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project nameImprovement of Geometrics of Thondupally to Kothur from Km 22.300 to Km 34.14 of NH-44SOURCE_BACKEDSource
Project code618560SOURCE_BACKEDSource
UPCsN/02010/01002/TSSOURCE_BACKEDSource
StageTerminatedSOURCE_BACKEDSource
Physical progress17.05SOURCE_BACKEDSource
Sanctioned cost542SOURCE_BACKEDSource
Revised cost527.43SOURCE_BACKEDSource
Public schedule16/09/2024SOURCE_BACKEDSource
Public revised scheduleEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Contractor CINEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Concessionaire SPV CINEVIDENCE_PENDINGNOT_APPLICABLESource
LenderEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Loan DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context
Approved revised DCCOEVIDENCE_PENDINGEVIDENCE_PENDINGGap / internal context

Source Web

  • NHAI Data LakePromoted UPC package status, stage/progress field, package identity, and contractor text where available.Open source route
  • PAIMANA / MoSPIProject spine, public cost/date context, and ministry monitoring reference.Open source route

Confirmed Checks

Stage Of CompletionTerminatedStage maps to same normalized Data Lake vocabulary family: TERMINATED.NHAI Data Lake
Physical Progress17.05Physical progress matches NHAI Data Lake.NHAI Data Lake
Contractor TextLakshmi Infrastructure & Developers India Pvt. Ltd.UPC contractor text matches NHAI Data Lake; this is not a CIN confirmation.NHAI Data Lake
NHNH44At least one NH token overlaps after title-token normalization.NHAI Data Lake
Cost Basistotal capital cost Rs 541.58 Cr; awarded/civil cost Rs 311 Cr; PAIMANA-public-cost, NHAI-total-capital-cost, and NHAI-awarded-cost may be different official bases.At least one public cost reconciles to NHAI total-capital cost basis.NHAI Data Lake

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

NHAI_TEXT_ONLY
NHAI contractor textLakshmi Infrastructure & Developers India Pvt. Ltd.
Exact CIN statusPending exact-CIN project link
Use in reportContractor text is context only until exact CIN is resolved

Open Gaps And Abstains

  • contractor_cin
  • lender
  • sanctioned_DCCO
  • approved_revised_DCCO
  • public_revised_scheduled_completion_date
Mixed PackageN/02010/01002/TS: Terminated; 17.05%Single-package row; mixed-package consistency check not applicable.NHAI Data Lake
Iig Nip Identityproject code=618560; project name=Improvement of Geometrics of Thondupally to Kothur from Km 22.300 to Km 34.14 of NH-44; nh tokens=NH44No exact IIG/NIP project-id match in local public crawl.IIG / NIP
Eprocure Aoc Awardpromoted upcs=N/02010/01002/TS; nhai award evidence=upc=N/02010/01002/TS; contractor name=Lakshmi Infrastructure & Developers India Pvt. Ltd.; awarded cost cr=311; date values=loa date=11-11-2022; agreement date=19-12-2022No exact tender_id mapping for this project in the eProcure AOC workbench.eProcure / ePublish
Ibbi Public Announcement Adverseresolved contractor cins=No resolved exact contractor CIN for this row; IBBI adverse adapter abstains.IBBI
Contractor CINCheckedNo exact project contractor CIN is available for automated Company Master confirmation in Phase 1.Public source route

15-Day Material-Change Tracker

  • Re-check promoted UPC, stage/status, physical field, cost basis, and scheduled date before sending externally.
  • Re-check contractor CIN, filings, rating/adverse routes, and material public disclosures before any borrower or contractor reliance.
  • If any source is unreachable, mark INSUFFICIENT_EXTERNAL; never treat absence as confirmation.

Satellite Visibility Appendix

  • Paid add-on only: two-date corridor construction-visibility review for ROW, formation, embankment, pavement texture, structures, and access activity.
  • Output is dated visual evidence, confidence notes, and LIE/site questions.
  • No satellite-derived public progress score. No stage certification. No engineering quality approval.

Reviewer Questions

  • Does the lender file contain sanctioned DCCO and approved revised DCCO that differ from public schedule dates?
  • Does the LIE/site team agree with the displayed official stage and the latest material-change status?
  • Is the borrower/concessionaire SPV legally distinct from the EPC contractor or listed sponsor?
  • Which open gaps must be closed before committee, renewal, disbursement, or portfolio action?
Not a stage certification.Not a credit rating.Not an RBI compliance certificate.No satellite-derived public progress score.External customer use requires audit and founder approval.
NONROAD-01 | Electricity Generation | 602579

Buxar Thermal Power Project [1320 MW]

SJVN; 99% minimum unit physical progress per CEA source route

SECTOR_SOURCE_CONTEXT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code602579
Official stateBihar
Capacity match basisofficial_state+paimana_total_capacity+cea_unit_aggregation_single_candidate
Capacity MW1320
Implementing agencySJVN
Physical evidence99% minimum unit progress
Strict-depth statusApproved in internal non-road source lane

Cross-Check Verdict

SECTOR_SOURCE_CONTEXT

Road Layer B is not applied to this sector.; CEA thermal source route provides official sector context.; Customer use requires a sector-specific audit before delivery.

Independent Set-A: cea_thermal_broad_status, paimana_mospi

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project code602579SOURCE_CONTEXTSource
StateBiharPOWER_OFFICIAL_STATE_FIELDSource
Capacity1320 MWAUDITED_CAPACITY_RECONCILIATIONSource
Implementing agencySJVNCEA_CONTEXTSource
Physical source99% minimum unit progressCEA_CONTEXTSource

Source Web

  • CEA thermal broad statusOfficial thermal project status / unit progress route.Open source route
  • PAIMANA / MoSPIProject spine, code, state, cost/capacity context.Open source route

Confirmed Checks

State + capacity + familyofficial_state+paimana_total_capacity+cea_unit_aggregation_single_candidateNon-road source-context match. It is not a road lender-grade report.CEA

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

SECTOR_ENTITY_CONTEXT_GAP
Agency roleSJVN
EPC contractorNot resolved in this sample
Use in reportNon-road context only until sector-specific contractor mapping is audited

Open Gaps And Abstains

  • Not a road/LIE dossier.
  • Implementing agency is not treated as EPC contractor.
  • Sector-specific customer use case needed before external delivery.
  • Latest CEA monthly report must be checked again before customer send.
Road Layer BNot run for non-road projectUse a sector-specific external reconciliation before customer delivery.Layer B road red-team

15-Day Material-Change Tracker

  • Re-check CEA monthly report and PAIMANA project spine before sending externally.
  • Add sector-specific contract award, implementing agency, lender, and commissioning source routes before paid delivery.
  • Do not mix this non-road source lane with road UPC truth gates.

Satellite Visibility Appendix

  • Satellite lane not activated for this non-road sample.
  • If selected later, imagery output must be sector-specific and audit-gated.
  • No satellite-derived public progress score.

Reviewer Questions

  • Is the customer asking for power-sector monitoring or only a product breadth sample?
  • Which sector source should be the stage/progress oracle before customer reliance?
  • Does the buyer need agency, EPC, owner, lender, or project-company intelligence?
Non-road context sample.No contractor matching without official source.Not a credit rating.No satellite-derived public progress score.
NONROAD-02 | Electricity Generation | 400231

NLC Talabira Thermal Power Project

NLC; 0% minimum unit physical progress per CEA source route

SECTOR_SOURCE_CONTEXT_REVIEW_SAMPLE

Executive Snapshot

PAIMANA code400231
Official stateOdisha
Capacity match basisofficial_state+cea_total_capacity+thermal_family_single_candidate
Capacity MW2400
Implementing agencyNLC
Physical evidence0% minimum unit progress
Strict-depth statusApproved in internal non-road source lane

Cross-Check Verdict

SECTOR_SOURCE_CONTEXT

Road Layer B is not applied to this sector.; CEA thermal source route provides official sector context.; Customer use requires a sector-specific audit before delivery.

Independent Set-A: cea_thermal_broad_status, paimana_mospi

Fail-closed rule: unreachable, absent, or rate-limited sources are gaps, never confirmations.

Evidence Field Map

Project code400231SOURCE_CONTEXTSource
StateOdishaPOWER_OFFICIAL_STATE_FIELDSource
Capacity2400 MWAUDITED_CAPACITY_RECONCILIATIONSource
Implementing agencyNLCCEA_CONTEXTSource
Physical source0% minimum unit progressCEA_CONTEXTSource

Source Web

  • CEA thermal broad statusOfficial thermal project status / unit progress route.Open source route
  • PAIMANA / MoSPIProject spine, code, state, cost/capacity context.Open source route

Confirmed Checks

State + capacity + familyofficial_state+cea_total_capacity+thermal_family_single_candidateNon-road source-context match. It is not a road lender-grade report.CEA

Holds / Contradictions

No material contradiction in the selected cross-check artifact.

Contractor / Entity Context

SECTOR_ENTITY_CONTEXT_GAP
Agency roleNLC
EPC contractorNot resolved in this sample
Use in reportNon-road context only until sector-specific contractor mapping is audited

Open Gaps And Abstains

  • Not a road/LIE dossier.
  • Implementing agency is not treated as EPC contractor.
  • Sector-specific customer use case needed before external delivery.
  • Latest CEA monthly report must be checked again before customer send.
Road Layer BNot run for non-road projectUse a sector-specific external reconciliation before customer delivery.Layer B road red-team

15-Day Material-Change Tracker

  • Re-check CEA monthly report and PAIMANA project spine before sending externally.
  • Add sector-specific contract award, implementing agency, lender, and commissioning source routes before paid delivery.
  • Do not mix this non-road source lane with road UPC truth gates.

Satellite Visibility Appendix

  • Satellite lane not activated for this non-road sample.
  • If selected later, imagery output must be sector-specific and audit-gated.
  • No satellite-derived public progress score.

Reviewer Questions

  • Is the customer asking for power-sector monitoring or only a product breadth sample?
  • Which sector source should be the stage/progress oracle before customer reliance?
  • Does the buyer need agency, EPC, owner, lender, or project-company intelligence?
Non-road context sample.No contractor matching without official source.Not a credit rating.No satellite-derived public progress score.